Changing/Displaying Data for Operation, Order or Capacity 

You can change or display operation data from the planning table (tabular form) in the following way:

  • Select the operation that you want to change or display and select the menu options Goto Operation and then, for example, one of the menu options Display, Change, Components or Prod.resource/tools.
  • If you want to change and/or dispatch or deallocate operations using your own enhancements, select the operations that you want to change and select the menu options Functions Extended planning User. You can find more information about user exits in User Exits.

Note that you can only call up an enhancement if the project to which it is assigned is activated.

If you want to change or display order data from the planning table (tabular form), select the menu options Goto Order and one of the menu options Display order or Change order.

If you want to change or display capacity data from the planning table (tabular form), choose Goto Capacity and one of the menu options Display capacity, Change capacity, or Reset capacity

You can find more information on maintaining work center data, capacity data and order data from the capacity planning table (tabular form) in Executing capacity leveling/planning sessions.