Use Operation and Order Floats for Dispatching 
Usage
You can specify that the operation float and also the floats before/after production for the order can be used when dispatching an operation.
The operation can then be dispatched within the float that was assigned to it in order scheduling.
Prerequisites
If you want to use the additional times for dispatching, activate the dispatching function Operation date check in the strategy profile and set the appropriate indicators.
|
If you want to use... |
set the indicators |
|
operation float |
Use operation float |
|
operation float + float after production |
Use operation float |
|
|
Use float aft. prod. |
|
operation float +float before production |
Use operation float |
|
|
Use float bef. prod. |
If you set the indicator Terminate dispatching on error then dispatching of the operation is terminated if the times are exceeded.