Usage
You can insert operations into an already existing capacity commitment. The operations that have already been dispatched are moved according to the planning direction but their sequence remains the same (see following graphic)
For example, with planning direction "forwards" if the operation to be dispatched has a start date that is earlier than or the same as that of an operation that has already been dispatched then the operation to be dispatched is dispatched before the operation that has already been dispatched. If the operation to be dispatched has a later date than the operation that has already been dispatched then it is dispatched after the operation that has already been dispatched.
If an error arises when moving operations then the operation is not inserted.

Prerequisites
If you want to use this function, set the indicator Insert operation in the strategy profile.