Scheduling Dispatched Activities in the Network 
Activities in networks that have the status "dispatched" have a predefined date from dispatching. The system treats this date as the constraint "must start on".
If the system schedules the network again, then it takes the time constraints in the network into account. Midpoint scheduling is not used for networks.
Please refer to the guide PS - Project System for more information on scheduling networks.