Rescheduling Planned Orders Taking Production Versions into Account 
Use
If you reschedule a planned order to another work center the planned order is automatically scheduled and dispatched using the appropriate production version of the material. The planned order takes over the production version in which the new work center is entered as the production line.
This function is available in both types of planning table. It is of interest for all areas that use planned orders, for example in repetitive manufacturing or in MRP/MPS. It can also be used in production control when later converting planned orders to production orders.
Prerequisites
If you want to implement this function the following conditions must be met:
- The indicator Reschedule with production version must be set in the strategy profile.
- The original work center
- must be entered in the production version of the material as the production line (not necessarily in the current production version).
- can only be assigned to one operation in the routing for this production version
- The target work center to which the operation is to be rescheduled
- must be entered in another production version of the material as the production line
- can only be assigned to one operation in the routing for this production version
Scope of functions
You can only reschedule main operations with this function but not suboperations.
Actions
If one of the conditions is not fulfilled then no new production version is copied to the planned order when it is rescheduled. In this case the system uses the formulas from the new work center and the original standard values for scheduling. If you want rescheduling to be terminated if one of the conditions is not fulfilled set the indicator Term. resched. with prod. version as well as the indicator Reschedule with prod. version in the strategy profile.