When an operation is rescheduled, a dispatched operation is moved to a new date and/or to a new work center. When this happens the system takes the capacity commitment at the target point into consideration. By dragging and dropping you manually reschedule operations (more precisely: by dragging an operation from the line in the work center chart and dropping it onto the desired point in time on the same or on another line in the work center chart). Proceed as follows:
- Place the cursor on the desired operation which has already been dispatched.
- Press the left mouse button and drag - by keeping the mouse button pressed down - the object surrounded by an outline to the new position (work center and point in time) in the same chart ("work centers").

In forward planning the system displays the left edge as the planning point in time, in backward planning, the right edge.
- Release the mouse button.

To reschedule several operations, you first have to deallocate them and then dispatch them again.