Changing the Standard Value for Setup Manually 
Use
You can manually change the setup times of selected operations in the planning tables.

This function is not available for capacity leveling in the process industry (PP-PI), that is, for capacity leveling of process orders and planned orders that refer to master recipes.
Prerequisites
Use only standard value keys for which the setup standard values are located at the same place (that is, for which the setup standard values have the same standard value number) for the work centers relevant for capacity leveling.
Procedure
- Select the operations for which you want to adjust the setup times.
- Choose
|
In the capacity planning table (graphic) |
Functions → Adjust setup time → Manual |
|
In the capacity planning table (tabular form) |
Functions → Extended planning → Adjust setup time |
- Enter the setup standard value for each operation with which the setup time should be recalculated.
- Choose Execute.
Procedure
The system reschedules the relevant orders, although it takes the new setup standard values into account.