Prerequisites
You can change orders in the planning tables, for example to adjust capacity requirements. Order data that can be changed includes the following:
- Order quantity
- Work center where the operation is to be carried out
- Order dates
Procedure
- Select the requirements that you want to change as a result of changing the order data. The order is determined using this selection.
- Choose the following menu options on the planning table: Goto → Order → Change order.

To call up a planning table with the work center view you specify one or more work centers. From within the planning table you can branch to the operations in an order and change the work center where an operation is to be processed. However, if the new work center was not one of those originally specified when calling up the planning table then the work center is not displayed in the planning table.