Creating Capacities by Copying from 
Prerequisites
When you create a capacity, you can use an already existing capacity to copy from. You can use either a work center capacity or a work center independent capacity.
Procedure
Work Center Independent Capacity
- On the initial screen for creating a capacity choose Copy from...
The Copy from dialog box appears.
- If you want to copy from a work center independent capacity (for example a pooled capacity), enter the capacity and the capacity category. If you want to copy from a work center capacity, enter the work center and the capacity category.
- Select the data that you want to copy to the new capacity.
Work Center Capacity
- On the initial screen for creating a work center enter the plant and the work center from which you want to copy.
The Copy from dialog box appears.
- Select the data that you want to copy to the new work center

In work center maintenance and capacity maintenance you can either copy or reference capacities.