Operation scrap is maintained for 2 material components in the BOM. One component is also subject to assembly scrap. The component quantities must be adjusted to include the scrap.
|
Quantity of material RB to be produced
Assembly scrap: |
1,000 pieces
10 % (pieces) |
|
Component 1: Operation scrap: Net indicator: → Scrap quantity |
no entry not selected → assembly scrap used in calculation 100 pieces |
|
Component 2: Operation scrap: Net indicator:
→ Scrap quantity |
1 % selected, therefore assembly scrap not used in calculation 10 pieces |
Before component 2 is built into the assembly, the faulty assemblies are taken out of the process, and only the operation scrap is calculated.
The quantity for component 1 is for 1,100 racing bicycles to be produced. The quantity for component 2 is for 1,010 racing bicycles to be produced.