Using Collective Access for Planning Result 

  1. From the MRP or MPS menu, select Evaluations Planning result collective display.

You now branch into the collective access screen.

  1. In collective access:
    • Enter the plant and one of the parameters MRP controller or product group.

If you do not enter any further selection criteria, the system selects all the materials assigned to this MRP controller or this product group in the respective plant.

    • If the work with MRP areas is activated for a single client: you enter either the plant (= all MRP areas including the plant MRP area) or only one particular MRP area, and, in addition, either the MRP controller or product group.

If you do not enter any further selection criteria, the system selects all the materials assigned to this MRP controller or this product group in the selected MRP area or in all MRP areas. Materials that are assigned to five MRP areas are displayed, where applicable, with five MRP lists.

  1. If required, enter further selection criteria.
    • Date: for example, all MRP lists that were created or processed within the last two weeks, or MRP lists for all materials with insufficient stock for the next two weeks.
    • Exception groups: for example, MRP lists for all materials for which the planning run was terminated (exception group 8).
    • Processing indicator: for example, all MRP lists that have not yet been processed.
    • Procurement: for example, MRP lists for all materials that are procured externally.
  1. Enter the layout.
  1. Choose twice.

The material list appears. This contains all the materials that fulfilled you selection criteria.

  1. Select one or more materials and choose Selected MRP lists.