Reorganizing Firmed Planned Orders 
Use
Firmed planned orders are subject to normal firming logic; that means, the system does not delete them automatically during the planning run when they are no longer needed. You can, however, define a roll forward period. The system then deletes all firmed planned orders that lie before the roll forward period automatically. The master plan is thus updated.
Prerequisites
- In Customizing for MRP or MPS in the IMG activity Define planning time fence and roll forward period, you have defined a roll forward period per plant or per MRP group.
- If you define it per MRP group, you have assigned the corresponding MRP group to the material in the material master.
- You have assigned an MRP type, which allows the deletion of firmed planned orders, to the material in the material master.