Use
Interactive planning is a single-level simulative planning. It enables you to check the planning result particularly carefully and to carry out fine tuning. It is particularly suitable for materials for which a thorough check is necessary, and above all for master schedule items (see also Master Production Scheduling ).
Features
In interactive planning the system first of all displays the stock/requirements list, but does not plan it directly. From this stock/requirements list you can trigger the planning and simulation functions manually.
With interactive planning you have the following possibilities:
- You can enter procurement proposals for materials procured in-house or externally.
- You can change or reschedule procurement proposals entered in the planning run.
- After each change you can carry out a rescheduling check and the planning (net and lot-size calculation).
All the changes are simulative first of all and are only written to the database after saving.
Activities
- Starting from the MPS node choose Master schedule items → Single-item, interactive or from the MRP node choose Planning → Single-item, interactive.
This takes you to the initial screen for interactive planning.
- Enter the data required, as described in Single-Item, Single-Level Planning .
The stock/requirements list display appears. The system has not yet carried out the planning.
- Choose
.
The planning is carried out and the system takes you to the planning result. This planning result only exists in the main memory and is not saved on the database.
- Deal with the planning result as desired.
For more information, see Working with the Planning Result .
With
you can also check the rescheduling.
- Run the planning again with
. - Repeat steps 4 and 5 as often as necessary.
- When you are satisfied with the planning result, save your data.
The planning result is saved to the database.