Example of Backward Scheduling for In-House Production 
Example Data
|
Requirements date |
25.6. (Friday) |
|
Goods receipt processing time |
2 days (workdays) |
|
In-house production time for the material: |
6 days (workdays) |
|
Opening period |
6 days (workdays) |
|
Workdays = Monday to Friday, no bank holiday |
|
Scheduling
- Requirements data minus goods receipt processing time = order finish date
25.6. (Friday) minus 2 workdays = 23.6. (Wednesday)
- Order finish date minus in-house production time = order start date
23.6. (Wednesday) minus 6 workdays = 15.6. (Tuesday)
- Order start date minus opening period = order opening date
15.6. (Tuesday) minus 6 workdays = 7.6. (Monday)