Creating Worklists 

Use

You want the system to create a worklist of particular materials in the material list.

Prerequisites

You have entered the required selection criteria in the collective access to the MRP list or stock/requirements list and have called up the material list of all the materials that correspond to these criteria.

The material list includes the following for each material: traffic light, ranges of coverage, the number of exception messages per exception group, the current plant stock, and various other material data.

Procedure

  1. In the material list, select the materials for which you want to display the MRP lists or stock/requirements lists:
    • individual materials by clicking on the line
    • all materials by using
    • a block of materials by clicking on the first and last line and then choose .

You can find the required materials in two ways:

  • with the search function in the material list using . For example, you search for all the materials with stocks that are sufficient for less than two weeks.
  • by sorting the material list using . For example, you sort the material list so that all materials for which an opening date in the past was determined (exception group 1) are displayed first.
  1. To access the appropriate list, double-click the first material or choose Selected stock/requirements lists or Selected MRP lists.

The system displays the list for the first material.

  1. Choose Show material tree.

Result

The system displays all the materials that you selected in the material list in a worklist tree on the left-hand side of the screen. Double-click the appropriate material in this tree, or choose and , to change from list to list.