Use
You use this function to plan the scrap of a component that may break during production of an assembly.
Prerequisites
You have entered values for calculating component scrap in the material master or the BOM:
- in the BOM on the Item Detail Screen: General Data (data block for quantity data). This component scrap is only relevant for the individual BOM.
- in the material master (view MRP 4) in the Component scrap field. This component scrap is relevant for all BOMs.

The component scrap quantity maintained for a material component in the BOM has the higher priority.
Features
- Component scrap increases the dependent requirements quantity of the component.
- If a scrap quantity was planned for a higher-level assembly, assembly scrap and component scrap are added to the component level.
Example
|
Estimate yield |
200 |
|
Assembly scrap |
10% |
|
Component scrap |
10% |
|
This results in a scrap quantity of |
42 pieces |
|
and a required quantity of |
242 pieces |