Copying Planned Independent Requirements Versions for LTP 

Procedure

To copy existing planned independent requirements versions to a simulative version, proceed as follows:

  1. Starting from the Long-term Planning node, choose Planned indep.reqmts  Copy version.

The system calls up the report Copy Version.

  1. Limit the selection of the existing versions using the following selection criteria:

– Plant

– Material

– Selection period

  1. In the section of the screen entitled, Version, enter the number of the existing version in the Source version field and the number of the simulation version in the Target version field.
  2. In the section of the screen entitled Change target version, you can change the quantities in the simulative version using various arithmetic operations and you can move them month by month into the future.

If you want to change the quantity in the simulative version, in the Change field, enter the quantity by which the individual schedule lines of the simulation version are to be changed and select the arithmetic operation to be used.

If you want to move the schedule lines of the simulation versions, enter the number of months in the Postpone by n month(s) field.

  1. The target version is not activated for long-term planning which means that the field, Target version active has not been selected.
  2. To carry out the report, you can also maintain the following settings:

– If you want a history of the copied version to be maintained, select the History field.

– If you want a list with the copied schedule lines after the report has been carried out, select the field, Create list of results.

– If you want to test the report in simulative mode first select the No data base changes (simulation) field.

  1. Once you have set all the parameters, choose Execute.

The source version(s) are copied with the specified selection criteria.