- From any work center screen choose Goto → Scheduling.
The Scheduling screen appears.
- Enter the capacity with its capacity category whose execution time you want to use for scheduling. This can be either a work center capacity or a pooled capacity.

The capacity data must have already been entered in the work center.
- Maintain formulas for operation segments (for production orders) or for internal processing time (for networks and maintenance orders).
If you do not enter a formula for an operation segment, the execution time of this segment is set to zero.
If you do not enter a formula for internal processing time, the duration in the network or maintenance order is used.
Via Extras → Formula you can assign a formula constant a value and an unit, display a formula and test formulas
- Maintain queue times and if necessary the dimension and units of measure for work in internal processing operations.