Sub-operations are not divided into individual operation segments in scheduling. The system schedules start and finish dates for the sub-operations from their reference dates.
To define the start and the finish of a sub-operation, you must maintain the following data on the Operation Details screen:
- a reference date (for example, start of setup or finish of the execution of the corresponding operation)
- an offset
- If the offset is positive, forward scheduling is carried out starting from the reference date.
- If the offset is negative, backward scheduling is carried out starting from the reference date.

If you have not maintained scheduling data for a sub-operation, the start date of setup and the finish date of execution are transferred to the sub-operation.