By scheduling routings, you can better control the lead times. When you create a routing, it is already possible to check the expected lead time and if necessary adjust the routing.
Routings are scheduled without reference to an order.
Proceed as follows to schedule a routing:
- Call up the operation overview for the routing.
- Choose Extras → Scheduling → Schedule.
You reach the Scheduling dialog box.
- Maintain the data on the dialog box. The system proposes forward scheduling for the scheduling type.
- Choose Continue.
You reach the Enter overview variant dialog box.
- Enter the overview variant you want to use to display the scheduling results. Choose Continue.
The routing is scheduled. You reach the Schedule Overview screen containing the scheduling data.
- After the scheduling run has been carried out, you can display
- the scheduling results
- a Gantt chart with scheduling results
- the scheduling log
You can also schedule all routings in a group at once. You can find further information on this topic in Updating the material master records