Creating a Production Resource/Tool as a Material 
- On the R/3 main menu choose Logistics → Production → Master data → Prod.resources/tools and then Prod.resources/tools → Material → Create general.
If the production resource/tool (PRT) is not to be used immediately but from a particular date in the future, choose Material → Create → Schedule
- Enter the relevant data on the initial screen.
You must enter a material type for which you can maintain the "Prod. resources/tools" view. An example of such a material type is FHMI in the standard system.
- Choose Enter.
The Select View(s) dialog box appears.
- Select the Production resources/tools view and any views for any other areas in which the PRT is to be used. Choose Continue.
The Organizational Levels dialog box appears
- Enter the plant, that you want to assign the PRT to, and if necessary organizational levels and profiles for the other views
If you have entered a material to copy from in the initial screen, additionally enter the organizational levels from which data is to be transferred.
- Choose Continue.
The first view appears.
- Enter the necessary data and then choose Next view..
- Repeat step 6, until you have edited all the views..
You use the MM/PP status to release the material for use as a PRT.
You cannot change the base unit of measure or the unit of issue after you have assigned the material as a PRT to operations.
- Save the material.
See also: