To create a subcontract order, proceed as follows:
- Enter the material you want to order and the item category for subcontracting (L) in the order item.
Press Enter to display the screen for component processing.
- Enter the components that the vendor requires to manufacture the ordered material (end product). Note the following:
- You do not need to enter the date required for the components. This date is proposed by the system when you press Enter. It is calculated as follows:
- Delivery date of the item minus planned delivery time
- If you do not want the quantity of the components to be changed if the order quantity of the end product is altered, set the indicator Fixed quantity.
- If you want to assign a particular batch of the component to the vendor for the manufacture of the ordered material, enter the desired batch.
- You can determine whether the components are available on the date required by selecting Component List → Component Availability.
- If you entered a bill of material as the material in the subcontract order, the components are created automatically.
If you want to determine the components in the bill of material at a later date (for example, if the bill of material is subsequently changed), choose Item → Goto → Components → New BOM explosion. The existing components are deleted and redetermined in the bill of material.
- Save the purchase order.
When you print the purchase order, the components are printed per order item.