Time-Phased Planning 

Use

If a vendor always delivers a material on a particular day of the week, it makes sense to plan this material according to the same cycle, in which it is delivered.

Features

Materials that are planned using the time-phased planning technique are provided with an MRP date in the planning file. This date is set when creating a material master and is re-set after each planning run. It represents the date on which the material is to be planned again and is calculated on the basis of the planning cycle entered in the material master.

The net change planning indicator and the net change planning horizon indicator are irrelevant for materials planned using the time-phased planning procedure. The system does not therefore set these if changes are made in the planning run.

If you want to plan a material earlier than the specified MRP date, you can enter an MRP date during the planning run. For example, if the planning run is set for Monday, you can bring it forward to Saturday instead.

If you use the SAP Retail System, the system proposes the planning cycle from the vendor sub-range when you create a material master record. The vendor sub-range contains all the goods of a particular vendor that, from a logistical view, can be planned similarly.

Time-phased planning can be executed using consumption-based planning or MRP:

  • If you want to carry out time-phased planning using consumption-based planning techniques, the requirements have to be created using the material forecast. If you use consumption-based planning, only the forecast requirements are included in the net requirements calculation. For reducing the forecast requirements, you can choose the same settings in Customizing as used for forecast-based planning.
  • If you want to carry out time-phased planning using MRP, all the requirements that are relevant to MRP are included in the net requirements calculation. For this purpose, the indicator Time-phased with requirements must have been selected in the MRP type. The forecast requirements can also be taken into account in this process.