Use
Scheduling is carried out in MRP after the system has calculated the quantity to be procured in the lot-size calculation. As the materials planned using consumption-based planing are externally procure, the following description is of scheduling for external procurement.
Scheduling determines the order start and the order finish dates of the procurement elements.
Prerequisites
- You must define the processing time for purchasing in workdays either in Customizing for MRP, in the plant parameters or in the workstep, external procurement.
- You must define the planned delivery time of the material in calendar days in the material master record (MRP 2 view).
- You must define the goods receipt processing time in workdays in the material master record (MRP 2 view).
Features
In forecast-based planning, the basic dates are calculated in backward scheduling, in reorder point planning, they are calculated in forward scheduling.
- This is the order start date and the order finish date of the planned order. The opening period is also taken into consideration in scheduling for the planned order.
- The following dates are calculated for the purchase requisition:
- Delivery date (corresponds to the order finish date)
- Release date (corresponds to the order start date)
Process Flow
Result