Excluding a Storage Location from MRP 

Use

You can exclude a storage location from MRP at plant level.

Prerequisites

You have set the MRP indicator for Storage location stock excluded from MRP for the storage location (Storage location MRP screen area) in the material master (MRP 4 view).

Features

  • The available warehouse stock at plant level is reduced by the stock in the storage locations that are to be planned separately. You can, however, still make withdrawals from this stock.
  • No net requirements calculation is carried out for these storage locations to be planned separately.